Wednesday, November
21st., 2007
8:10 Am
Nov
7,
9,
10,
11,
12,
15,
17,
19,
20,
21,
The workers have the
day off today for our main contractor and for our own people (17). We
sub-contracted out the outside rendering to a local firm from Chalong. They
finished A 502 room and now will start on A 501. They are also to start the
outside today also. We have a large 3 x 12 sign arrive from Bangkok and we
will be putting that on top of Building A. About 50% of the brickwork is now
done on Building B and we hope to have it 100% done in the next two weeks.
The contractor handed over the job yesterday and is now finished with
building B. We plan to pour the 3rd floor of C building on the 26th of this
month. Tomorrow they should will start placing the plate slab on that floor.