Friday, November
23rd., 2007
8:10 Am
Nov
7,
9,
10,
11,
12,
15,
17,
19,
20,
21,
22,
23,
24,
The main contractor
is working on getting the 3rd floor ready to pour on the 26th. We
have 10 new workers starting tomorrow that will be rendering Building A. Our
carpenters are building a large 3x12 meter sign on top of building A. Our
bricklayer will start 5th floor of B tomorrow and we will start rendering
all the rooms with a new crew tomorrow. Today we need to build extra housing
for 10 additional workers that should arrive tonight.