Tuesday, November
27th., 2007
11:50 Am
Nov
7,
9,
10,
11,
12,
15,
17,
19,
20,
21,
22,
23,
24,
25,
26,
27,
28,
The main contractor
will start now on making the columns on the 3rd floor of Building C. Should
pour December 1st. Our steel arrived for the 4th floor today, plus brick,
sand, cement, etc. Building A large project sign on the top of A building.
Bricking in the3rd,4th and 5th floors of B building this week. Doing the
final touches on A building before the inside and outside render contractors
start their work
Photos:
   
   
 