Thursday,
December 6th., 2007
11:50 Am
Dec
1,
3,
4,
5,
6,
7,
Well after a well deserved holiday we are all back
at it. Our contractor is removing the formwork off the 3rd floor columns and
getting ready to start the next floor. We have asked they start turning over
the floors faster so we are planning the 4th floor on December 20th and
columns on the 24th. Our brick layers are finishing building B up and will
be starting on C soon. The outside rendering team of 12 people are doing A's
outside. We have wiring and air conditioning going in A 202 right now.
   
   
   
   