Monday,
December 10th., 2007
11:50 Am
Dec
1,
3,
4,
5,
6,
7,
10
Our contractor was started to do the steelwork on
the 4th floor of C building for a pour on the 20th of this month and columns
on the 24th. We have been working a lot of overtime at night getting that
ready. Our workers have the brickwork in Building B almost done and we will
be starting rendering that building soon also. The rendering in Building A
is coming along pretty good also. Every day I see that have a little more
done on every floor. We started the brickwork on ground floor of B today and
will start the ground floor of C tomorrow with about 6 workers.
   
   
   
   
   
   