Tuesday,
December 11th., 2007
11:50 Am
Dec
1,
3,
4,
5,
6,
7,
10,
11,
13,
Our contractor has a great start on the 4th floor
for the pour on the 20th of this month. The bricklayers have started on C
building this morning doing the ground floor. We are waiting for the 2nd
floor to clear to start electric up there. Pluming is doing some finish work
in A building and electric in B and C. Doing the last of the Brickwork in
the stairs of B building now and the ground floor. Building our Ad on the
roof of Building A. Lot's going on this month as we push to finish for next
year.
   
   