Our contractor has the 4th floor almost ready to
pour for tomorrow. The bricklayers are working on B final work
and C building ground floor. We have started the 2nd floor
electric. Pluming is doing some finish work in A building. Also doing a lot of final work in A
building to get that finished. Demo unit in A is getting the ceiling
installed.