Saturday Jan.
20th, 2007 8:45 Am
1,2,3,4,5,6,8,9,10,11,12,13,14,17,18,18
cont.,19,20,21,
The crew is still working on forming the lift core and basement stairs. The are
also getting ready to pour ground floor ring beam.
We will be starting Building B very soon. Because the building doesn't
have a basement the construction will go very quickly. Next week I hope to
get the land pegged and start bore piling the area.
Building A construction:
   
   
   
   
   
Steel arrival: We got in 24 tons of rebar late yesterday. I worked with
the guys until 9:30 last night unloading it because it had to be all
unloaded by hand because of it's length. The plus to this is the steel is
all straight and doesn't need to be straightened like you see in
many of the photos.
  
Building B:
Soon to start here. We already ordered the
pilings and will begin the pegging next week. Here is also the piling plan
for that building and the rest of the project. This is last to go in and
the project is 100% piled. Sorry to remove the demo but something had to
give.

 
Last years photos
here