Thursday Jan.
25th, 2007 10:09 Am
1,2,3,4,5,6,8,9,10,11,12,13,14,17,18,18
cont.,19,20,21,22,24,25,26,
Building A - Working on the ring beam. The lift core base is poured.
  
Later in the day we poured some concrete.
   
   
   
   
   
   
   
   

Building B- Pegged and ready to pile.
 
Building B perspective model photos:
   
   
  
Last years photos