Sunday Feb.
11th, 2007 8:49 Am
Feb 1,
2, 3,
4,
5,
6,
7,
8,
9,10,
11,18,
Today they will continue to strip down the forms.
The structure for the basement /1st floor is just about finished. We will
pour the deck after the concrete plate arrive. Should be mid week. They
are also pounding out the pilings for Building B. It's really shaking the
hell out of my office.
   
   
10:30 Am:
   
   
 
*****************************************************************
Here is some land I saw last night on my way to eat seafood. Looks like
they are clearing it for a housing project. This was in Chalong.
   
Last Months photos below:
Jan 1,2,3,4,5,6,8,9,10,11,12,13,14,17,18,18
cont.,19,20,21,22,24,25,26,27,29,31,
Last years photos
here