Friday Feb.
2nd, 2007 11:20 Am
Feb 1,
2,
3,
Building A - Busy day here. We have a man in to spray the building
for bugs before the dirt is backfilled. SAC is forming up the next 50% of
the ring beam for pouring on Monday. We have a backhoe in today doing some
general backfilling and land leveling for the Piling machine to Pile
Building B soon.
Photos: General site Building A
  
Termite protection:
   
   
   
   
   
   
   
   
   
   
   
 
Below is a photo of a home office building I went to look at in Phuket
Town. They are using plastic forms instead of wood forms for the
structure. I want to see what the finish was like on the posts and beams.

Last Months photos below:
Jan 1,2,3,4,5,6,8,9,10,11,12,13,14,17,18,18
cont.,19,20,21,22,24,25,26,27,29,31,
Last years photos
here