Tuesday Feb.
6th, 2007 10:40 Am
Feb 1,
2, 3,
4,
5,
6,
7,
The last of the forming is being made today for the pour for tomorrow. The
first floor should be well on the way after tomorrow. They just dropped
off the first 8 pilings for Building B. Tomorrow will be very busy as we
will have a crane in and several concrete trucks.