Today we are pouring the lift core for buildings A
and B. Building A is the first floor columns for the lift core and another
column that not finished on the stairwell. They are also pouring a small
stairwell slab.
Today's photos for Building A:
   
   
   
 
We are pouring the below ground level of the lift core for
Building B. They are getting ready to form up the beams for building. many
photos are dark because now it rains often. Sometimes 2-3 times in one day.
Today's photos for Building B:
   
   
   
   
   
 
The weather turned pretty bad before the pour was finished.
  
Today's video:
http://vids.myspace.com/index.cfm?fuseaction=vids.individual&videoid=2028055873
Feb 1,
2,
3,
4,
5,
6,
7,
8,
9,10,
11,12-17,18,19,20,21,22,
23,
24,
25,
26,
27,
28,
Mar
1,
4,
7,
8,
9,
10,
11,
12,
13,
15,
16,
19,
23,
24,
26,
28,
29,
31,
Apr
1,
4,
5,
6,
7,
8, 9,
10,
11,
17,
18,
19,
20,
21,
22,
23,
24,
25,
26,
27,
28,
29,
30
Last years photos
here
Ready to buy ? Download our
reservation form today !
|