Today the workers are doing the steel work and forms on
Building A. Getting ready to pour the slab on C and the slab on A on the
16th and the columns on the1st floor on the 20th. We will also pour the the
5th floor of Building A on the 20th. I see this morning they are starting in
doing the frame work on building B's 4th floor. We should be pouring that
floor on the 26th.The M & E contractor is getting the 2nd floor conduit ran for
pluming and wires. We start resuming brick work tomorrow. Our 1st kitchen
arrived and should be in later today.
Today's Photos of Building A:
   
   
   
   
M & E on A 201

Today's Photos of Building B:
   
   
   
Today's Photos of Building C:
   
   
  
More shots of A building:
   
   
 
End of Day:
   
   
   
   

Our kitchen arrive late in the day:
  
NEW Perspective Photos:
   
   
   
   
   
   
############################################################
Feb 1,
2,
3,
4,
5,
6,
7,
8,
9,10,
11,12-17,18,19,20,21,22,
23,
24,
25,
26,
27,
28,
Mar
1,
4,
7,
8,
9,
10,
11,
12,
13,
15,
16,
19,
23,
24,
26,
28,
29,
31,
Apr
1,
4,
5,
6,
7,
8, 9,
10,
11,
17,
18,
19,
20,
21,
22,
23,
24,
25,
26,
27,
28,
29,
30
May
2,
4,
5,
6,
7,
8,
9,10 -15,
16,
17,
18,
19,
20,
21,
22,
23,
24,
25, 26,
27,
28, 29,
30,
31
June
1,
2,
3,
4,
7,
8,
9,
10,
11,
12,
13,
14,
15,
16,
17,
18,
19,
20,
21,
22,
23,
24,
25,
26,
27,
28,
29,
30,
July
1,
2,
3,
6, 8,
10,
11,
12,
13,
14, 15,
16,
17,
18,
19,
20,
21,
22,
23,
24,
25,
26,
27,
28,
29,
31,
Last years photos
here
Ready to buy ? Download our
reservation form today !
|