Tuesday
January 22nd., 2008 1:30 Pm
Jan
1,
2,
3,
4,
5,
6,
7,
8,
9,
11,
12,
14,
15,
16,
18,
19,
21,
22,
24,
We are working on finishing A building rendering
inside room and hallways. Staring on doing the roof last pour for building
C. After C is done, our main contractor will be moving off of the site and
we will start the swimming pool and project walls while we continue to
finish the inside and outside of the three buildings. Steel arrived to
finish the roof.